Office Fit Out Cost in London 2026: £ Per Sq Ft

London Cat B office fit-out runs £65–£175 per sq ft net in 2026. What sits inside the rate, the figures that shape your layout, and what the rate leaves out.

By Vladimir Castravet··
Completed commercial fit-out by 2VP in a London heritage building — stone stair, new lighting and finished circulation space

London Cat B office fit-out runs £65–£175 per square foot, net of VAT — on a 2,500 sq ft suite, £162,500 to £437,500. Two contractors can quote the same floor plate £100,000 apart while both being honest, because the rate compresses five different budgets into one number and quietly leaves four more outside it.

A per-square-foot rate is a summary, not a price. This guide opens it up: what sits inside the rate, the compliance figures that decide your layout before a designer touches it, and the costs the rate does not carry.

Our commercial fit-out page sets out how we work on the delivery side, and it deliberately has no estimator on it — our pricing engine has eight project types and every one of them is residential, so a floor area cannot price an office. A fit-out is priced from a walk round the floor.

The three bands

These are our own bands for the sub-5,000 sq ft London market, all net of VAT.

BandWhat you get£/sq ft2,500 sq ft
EssentialOpen plan, light reconfiguration, a meeting room or two, tea-point, decoration, re-lamp, minimal M&E change£65–£80£162,500–£200,000
BalancedFull Cat B — glazed partitions, cellular meeting rooms, joinery tea-point, new lighting and small-power, acoustic treatment, good finishes£95–£120£237,500–£300,000
SignatureDesign-led scheme, bespoke joinery and reception, acoustic pods, integrated AV, feature finishes, significant M&E rework£135–£175£337,500–£437,500

Cat A landlord base build sits below these, at roughly £35–£65 per sq ft. For scale at the top end, Turner & Townsend's Global Office Fit-Out Cost Guide 2026 puts London high-specification fit-out at about £4,397 per m² — roughly £409 per sq ft, second in the world behind New York. A premium corporate scheme is a different product from a 2,500 sq ft suite, and the gap between that figure and the table above is specification, not sharp practice.

What you are actually buying

You are not paying for square feet. You are paying for the gap between what is there and what you need — which is why the same floor area produces two honest quotes a hundred thousand pounds apart, and why a rate found online was built for a different building in a different condition.

Note what the range is not. It is not a quality ladder where Essential means badly built. Essential means less is being built: fewer partitions, less M&E rework, simpler joinery. The workmanship standard should be identical in all three, and if a contractor's cheap band is cheap because the standard drops, that is not a band — that is a different contractor.

What sits inside a per-square-foot rate

Take the middle of the Balanced band — £107.50 per sq ft on 2,500 sq ft, £268,750 net — and split it across the five budgets a Cat B scheme actually contains. The shares below are indicative, not a published benchmark: they are the apportionment we use to interrogate a tender, and yours will move with the scheme.

ElementIndicative share£ net£/sq ft
Builders' work — partitions, ceilings, floors, joinery, decoration~41%110,18844.08
Mechanical & electrical — HVAC, power, lighting, fire, BMS~25%67,18826.88
Security, IT and AV — structured cabling, comms room, access control~13%34,93813.97
Furniture and FF&E~12%32,25012.90
Professional fees — design, M&E, building control, CDM~9%24,1889.68
Total100%268,750107.50

Two practical consequences follow, and they matter more than the exact percentages.

M&E is a quarter of the money and most of the risk. On services-heavy schemes it runs materially higher. If the existing VRF is at end of life, or the landlord's floor boxes are in the wrong places, that single element moves your total more than every finish decision combined. Establish the condition of the services before you fix a budget, not after.

Furniture and IT are frequently quoted out. A quarter of the total sitting in someone else's budget is how a fit-out comes in "on budget" and still costs a quarter more than expected. Ask every contractor, in writing, which of those five lines their number includes.

Cat A, Cat A+ and Cat B — check what you are inheriting

Cat A — the landlord's base Raised access floor, suspended ceiling, basic lighting, primary HVAC, finished perimeter walls, a compliant means of escape. A serviced blank, roughly £35–£65 per sq ft when the landlord builds it, and nothing about it makes it a workspace.
Cat B — your fit-out Layout, partitions, meeting rooms, tea-point, joinery, branding, finishes, AV. This is what the £65–£175 range prices. It is also the part you may be obliged to remove at the end of the lease.
Cat A+ — fitted and ready A landlord-funded, furnished, plug-and-play suite. Savills reported through 2025 that a large share of sub-5,000 sq ft Central London supply is now fitted — so for small suites this is a normal product rather than an exception.

The expensive mistake here is assuming you are taking Cat A when you are taking a previous tenant's Cat B. Inherited partitions in the wrong places are worse than an empty floor: you pay to remove them, you dispose of them, and you may be inheriting their reinstatement obligation too. Get the base condition confirmed in the heads of terms.

The two documents

The rate answers "how much per foot". The lease answers "how much in total". Read the alterations and yield-up clauses before you brief a designer.

The compliance figures that shape the layout

A fit-out is a regulated building project, not decoration. These figures decide how many meeting rooms fit on your floor and where the corridor can run.

The rules that shape a London office fit-out
WhatThe requirementSource
Escape travel distanceFor offices, maximum travel is 18 m where escape is possible in one direction only, and 45 m where it is possible in more than one direction.Approved Document B Volume 2 (2019), Table 2.1, purpose group 3
Occupancy for escapeWhere actual numbers are not known, an office is calculated at a floor space factor of 6.0 m² per person. A meeting or conference room is 1.0 m² per person.Approved Document B Volume 2 (2019), Table D1
Fresh air supplyOccupiable office rooms take the higher of 10 litres per second per person or 1 litre per second per m² of floor area.Approved Document F Volume 2 (2021), §1.32
Circulation spaceCorridors and lift lobbies: natural ventilation openings totalling at least 1/50 of the floor area, or mechanical supply at 0.5 l/s per m².Approved Document F Volume 2 (2021), §1.33
Rooms with no openable windowExtract must run while occupied and for a minimum of 15 minutes after occupants leave — which catches most internal meeting rooms and pods.Approved Document F Volume 2 (2021), §1.31
Print roomsRooms with printers or copiers in substantial use — more than 30 minutes per hour — need 20 l/s per machine during use, and should not be designed to be occupied.Approved Document F Volume 2 (2021), §1.25
Door widthsMinimum effective clear width in an existing building is 750 mm straight on, or 775 mm at right angles to an access route at least 1200 mm wide. New buildings: 800 mm and 825 mm.Approved Document M Volume 2, Table 2
Accessible WCAt least one wheelchair-accessible unisex toilet at each location where sanitary facilities are provided. Where there are four or more cubicles in separate-sex accommodation, one must be an enlarged cubicle.Approved Document M Volume 2, §5.7
Fire risk assessmentThe responsible person must make a suitable and sufficient assessment of fire risk, and review it when the premises change. A fit-out changes the premises.Regulatory Reform (Fire Safety) Order 2005, art. 9
Space per personThe Approved Code of Practice to the workroom-dimensions requirement gives 11 cubic metres per person as a minimum, ignoring headroom above 3 m.Workplace (Health, Safety and Welfare) Regulations 1992, reg. 10 and ACOP L24
CDM dutiesCommercial clients have no domestic exemption. A Principal Designer and Principal Contractor must be appointed in writing where more than one contractor is involved.Construction (Design and Management) Regulations 2015, regs. 4–5
EPC on lettingSince 1 April 2023 a landlord may not continue to let a non-domestic property with an EPC rating below E, unless a valid exemption is registered.Energy Efficiency (Private Rented Property) (England and Wales) Regulations 2015

Approved Documents are statutory guidance to the Building Regulations 2010 for England. Compliance is judged against the Requirements in Schedule 1; the Approved Document shows one way of meeting them. Your building control body has the final word on your specific building.

Approved Documents are statutory guidance to the Building Regulations 2010 for England. Compliance is judged against the Requirements in Schedule 1; the Approved Document shows one way of meeting them, and your building control body or approved inspector has the final word on your building.

Three of those numbers do most of the damage to a space plan.

The 18-metre dead end. A run of glazed offices down one side of a floor plate creates a corridor with one way out. Eighteen metres goes quickly. This is the single most common reason a beautiful first layout comes back from the fire engineer marked up.

The two densities. The BCO 2023 occupational density standard is 10 m² per person, so a 2,500 sq ft (232 m²) suite holds about 23 desks. Escape is calculated at 6.0 m² per person — the same suite is designed for about 38 people getting out. Those are two different numbers doing two different jobs, and confusing them produces either an undersized escape strategy or an oversized services design.

The ventilation crossover. Ten litres per second per person divided by ten square metres per person is exactly one litre per second per square metre. So at the BCO standard density the two Part F rules give the same answer — here, about 232 l/s. Densify past 10 m² per person and the per-person rule takes over, and your ventilation design has to grow with your headcount.

What moves a project between the bands

Cellularisation. Every glazed meeting room adds partition, door, ceiling adjustment, lighting circuit, ventilation and — if it has no openable window — a run-on extract. Partition count is the fastest way to walk from Essential to Balanced.
Condition of the M&E. Reusing serviceable HVAC keeps you low in the band; replacing end-of-life VRF puts you at the top of it. Worth establishing with a condition survey before you commit to a number.
The building itself. Goods lift availability, loading bay hours, single-stair access, protected working hours. A good building can be around 10% cheaper to fit out than a difficult one for identical drawings.
Access, specifically. A ground-floor unit with its own door is not the same job as a fourth-floor suite sharing one goods lift on a booking system with a two-hour window. Every delivery, every skip and every strip-out load goes through that window, and the programme is built around it rather than around the work.
Out-of-hours working. An occupied building pushes noisy work into evenings and weekends, at premium labour rates and with reduced productivity.
Acoustics. A partition specified to Rw 40–45 dB under BS 8233 is a different product from a standard stud, with different heads, seals and detailing. Worth paying for, and worth knowing you are paying for.
Programme. Under 5,000 sq ft usually runs six to eight weeks on site, with four to eight weeks of design, consent and procurement in front. Compressing that costs money in overtime and in premature ordering.

The costs the rate does not carry

  1. 01Licence to Alter. The landlord's consent pack — drawings, specifications, M&E information — plus the landlord's surveyor's and solicitor's fees, which the tenant normally pays. It is also, routinely, the longest item on the programme.
  2. 02Dilapidations on the space you are leaving. Reinstatement is commonly quoted in the London market at roughly £15–£35 per sq ft depending on how far back you must strip, and it is negotiated under the RICS dilapidations protocol rather than paid as claimed. On 2,500 sq ft that is a five-figure sum falling in the same year as the new fit-out. Get your own surveyor's assessment rather than budgeting from the landlord's schedule.
  3. 03Contingency. Hold 5–10% on a modern building and closer to 10–20% on older stock. In a building whose services you cannot fully survey until you open the ceiling, contingency is not padding — it is arithmetic.
  4. 04VAT. Every figure on this page is net. VAT is in addition at the standard rate. Most commercial tenants recover it, which is exactly why the honest way to quote a business is net — and why we do.
A declaration you are entitled to weigh

We deliver commercial fit-out, and windows and glazing come from our own AtoZ Design & Glass, so we profit directly from the partitioning line inside that builders'-work share. Read our enthusiasm for glazed offices with that in mind — and note that the section above tells you partition count is the fastest way to increase your bill.

When a fit-out is the wrong answer

Sometimes the right advice is not to build.

When the lease is too short. Amortising a £268,750 fit-out over three years is about £89,600 a year of hidden occupancy cost, before rent. Under five years, a fitted suite is often simply better value.
When you do not yet know your headcount. Hybrid working has moved desk ratios. A fixed cellular plan built around a headcount you are still arguing about is the most expensive way to discover you were wrong. Build less, and build it flexibly.
When the building will not support the ambition. If the landlord's HVAC cannot serve your density and the lease will not let you touch the risers, no amount of fit-out budget fixes it. That is a decision to move, not a decision to spend.
When furniture and paint would do. A tired office is often a decoration, lighting and furniture problem wearing a fit-out costume. That job sits below the Essential band entirely, and any contractor who tells you so is worth keeping.

The case for building properly is real, though. Where you hold a long lease, know your headcount, and the building's services are sound, a considered Cat B is the cheapest per year of anything on this page — and the difference between a floor people want to come to and one they tolerate is made of partition acoustics, daylight and air, all of which are on this list.

How to budget your own fit-out before you go to tender

  1. 01Confirm the base condition in writing. Cat A, Cat A+, or a previous tenant's Cat B. It decides where in the range you start and whether you are inheriting a strip-out.
  2. 02Read three clauses of the lease first. Alterations, reinstatement, yield-up. They set the dilapidations liability you create on the day you install a partition.
  3. 03Fix the density before the layout. Net internal area divided by your real m² per person. The BCO 2023 standard is 10 m² per person — use your actual figure, not your aspiration.
  4. 04Test the plan against escape distances. 18 m one direction, 45 m more than one. Do it on a sketch, before a designer has spent a fortnight on the drawing.
  5. 05Survey the services. Age and condition of HVAC, distribution capacity, floor box positions. A quarter of your budget and most of your risk lives here.
  6. 06Price the five elements separately. Builders' work, M&E, security/IT/AV, furniture, fees. Then add Licence to Alter, dilapidations, out-of-hours and contingency as named lines.
  7. 07Issue your document, not theirs. Give every contractor the same element breakdown in your order, and require them to price it that way. Comparable tenders are created by the document you send out, never by the ones that come back.

The same discipline, applied to a smaller job, is set out in two quotes, same job — what is inside the price. And the detail that decides whether a partitioned floor performs the way it was drawn is in fire-stopping, before the walls are closed.

What working in an open building actually costs

We deliver commercial fit-out in buildings that stay open while we are in them — Cat A and Cat B works inside the V&A’s Europe 1600–1815 galleries, and retail on Sloane Street.

The lesson from that work is not the one people expect. On a job like that the finish is rarely what drives the cost. Working around a building that is still open is. Restricted hours, protection of everything you are not touching, one delivery window, and the place spotless before the doors open in the morning. None of it shows in a photograph, and all of it is in the price.

The four things that let somebody price it properly

Any number given without seeing your building is a guess, and you pay for a guess later. Hand a contractor these four and the guessing stops.

  1. 01The size and the floor. Net internal area, which floor it is on, and how you get materials in and waste out. Not the postcode — the floor.
  2. 02The condition of the space today. Cat A, Cat A+, or a previous tenant's Cat B still standing. And the age and state of the services, because that is where a quarter of the budget and most of the risk lives.
  3. 03What you actually need in it. Desk numbers, meeting rooms, whether the tea-point is a counter or a kitchen, and which of it is fixed. Open plan with a simple kitchen sits at one end; acoustic pods, feature joinery and a proper reception sit a long way from it. Both are legitimate — they are just different buildings.
  4. 04Your dates, and the building's rules. When you need to be in, and whether the landlord permits work in normal hours. Nights and weekends are not a small uplift; they change the labour rate across the whole programme.
Common questions

Straight answers

The 2VP Certainty Package

The home you actually want, finished on the date in the contract — and you watch every day of it happen from your phone.

Your number in 60 secondsItemised stage breakdown in 2 minutesSurvey within 7 days

You answer 3 questions. We do the drawings, planning, party wall, trades and snagging.

Before anything is signed
Full measured survey + 3D design visualisation
You see the finished room before you commit to building it
£1,500
RIBA architect design by Nick Elias
Concept, planning and technical drawings by one named architect
£8,000–£15,000
Completion date written into the contract
A date you can plan a life around, not 'TBC at build start'
Included
While we build
No variation without your written approval
Nothing is added to your bill that you did not sign for first
Included
Friday video walkthrough of your site, every week
You know what happened this week without driving over
£1,200/yr
One named project lead, one channel, 24-hour response
You never chase a company — you message a person
Included
Daily photo diary + client dashboard
Everything photographed before it is covered up
Included
Fixtures at our trade pricing, passed through at cost
Our discount is yours, not a margin we keep quiet about
10–20% on materials
After we hand over
6-month snagging visit
We come back once the house has moved and settled
£750
12-month workmanship warranty on second-fix fittings, signed by the trades
The people who built it are on the hook for it, by name
Included
Annual check-ins for 2 years
We come back. Every year. No charge.
Included
Our guarantee
We finish on the agreed date, or we pay you £500 for every week we are late.
The date is in the contract, and so is this. Only a variation you approve can move it.
What you are not risking
  • 10% to mobilise, then weekly against work already done — with 5% held past handover: 2.5% released at practical completion and 2.5% at the end of the 12-month defects period
  • £550 survey fee credited in full against your contract
  • Every variation priced and signed before a penny is spent
4.8★ from 16 Google reviews — including the 1-star, published in full.
Get my price in 60 seconds

No email needed to see your range. Quotes hold for 21 days, then materials re-price.

We are not the cheapest. If price is the only factor, we may not be the right fit — and that is fine.

Get my price in 60 secondsBuilders in your areaAll cost guides
If this is your project

The home you actually want, finished on the date in the contract — and you watch every day of it happen from your phone.

How fast
  • Your number in 60 seconds
  • Itemised stage breakdown in 2 minutes
  • Survey within 7 days
What you do

You answer 3 questions. We do the drawings, planning, party wall, trades and snagging.

What protects you
  • 10% to mobilise, then weekly against work already done — with 5% held past handover: 2.5% released at practical completion and 2.5% at the end of the 12-month defects period
  • £550 survey fee credited in full against your contract
  • Every variation priced and signed before a penny is spent

The date is a term of the contract. We finish on the agreed date, or we pay you £500 for every week we are late.

Do not take our word for it

4.8 from 16 Google reviews

Every review is published in full on our reviews page, including the one-star. Google is the only platform we quote a rating for, because it is the only one we can evidence.

★★★★★
As a structural engineer, I've collaborated with 2VP Projects Ltd on several residential projects in London. Their attention to detail, proactive site management, and clear communication make every stage—from design to execution—smooth and efficient. It's rare to find a contractor who values both precision and professionalism at this level. A truly reliable partner.
Igors Smirnovs · Structural engineer we have worked with · June 2025
★★★★★
Great company to work with. Professional, reliable and easy to deal with. Vladimir and the team are always responsive, straightforward and genuinely care about doing things properly. I've had a very positive experience working with 2VP and would happily recommend them.
Sheen Delicatessen · Business client · August 2026
★★★★★
Extension went smoothly from start to finish. Communication was great throughout, and the team delivered exactly what we asked for. Thank you, 2VP!
Dan Martea · August 2026
Warranties and protections

What is covered, and by whom

A builder’s own guarantee is worth exactly as much as the company standing behind it. Here is what comes as standard, what you can add, and what has to come from somebody other than us — set out in full on our insurance and guarantee page.

Included in the contract
  • 12-month workmanship warranty on second-fix fittings
  • £5M public liability
  • £10M employer's liability
  • £2M professional indemnity
Optional, on request
  • HomePro insurance-backed guarantee, 10 years
  • Priced at 2.5% of the contract sum
  • Underwritten by an insurer, so it survives us
Not from us
  • 10-year structural warranty on a new dwelling (NHBC / LABC / Premier)
  • Professional fees — architect, engineer, building control
  • We will tell you when you need one rather than let you find out