Extend or Just Renovate: One House, Two Prices

We priced the same Battersea terrace twice — with the rear extension and without. The gap was £38,532 and four weeks, and 68% of it sat in two trades.

By Vladimir Castravet·
Inlaid marble floor at a gallery threshold in a London fit-out by 2VP, showing the level change between two finished spaces

From our V&A Museum project — South Kensington, SW7

We priced the same Battersea terrace twice against the same architect's drawings — once with the single-storey rear extension, once without. The difference was £38,532 of a £169,780 net quotation, or 22.7%, and four weeks off an eighteen-week programme. The useful part is not the headline. It is that 68% of that saving sat in just two of thirteen sections, and two sections did not move at all.

Most people asking whether an extension is worth it are handed a rate per square metre. That answers a different question. What a homeowner with drawings in hand actually wants is: on my house, with my scope, what happens to the number if the extension comes out — and what happens to everything else?

This is that comparison, from a real tender. The client, the address and the consultants stay out of it; the area and the money do not.

The two prices

The same house, priced both ways — net of VAT
WhatThe requirementSource
With the rear extensionFull house refurbishment plus a single-storey infill side and rear kitchen extension. Eighteen-week programme.£169,780.00 net
Renovation onlyThe same refurbishment, same first floor, no ground-floor extension. Fourteen-week programme.£131,248.10 net
The difference22.7% of the larger figure, and four weeks of programme.£38,531.90 net

Approved Documents are statutory guidance to the Building Regulations 2010 for England. Compliance is judged against the Requirements in Schedule 1; the Approved Document shows one way of meeting them. Your building control body has the final word on your specific building.

Both figures are net of VAT, which is charged in addition at 20%. Both were measured from the same tender drawings rather than estimated, which is what makes the comparison worth anything: the only variable between them is the extension.

Where the £38,532 actually sits

The thirteen sections are identical in both quotations, so the difference can be read line by line. Sorted by how much each one moved:

Section by section — what the extension adds, largest first
WhatThe requirementSource
Build-ups£42,205 with the extension, £25,961 without. Floor build-ups, the warm flat roof, cavity and party walls, partitions.−£16,244 · 42% of the difference
Structure£21,880 with, £11,890 without. The steel frame, foundations, padstones, fire protection.−£9,990 · 26%
Preliminaries£18,420 with, £14,800 without. Scaffold, protection, permits, waste, insurances — four fewer weeks of them.−£3,620 · 9%
Drainage and waste£6,280 with, £3,856 without. The extension built over a manhole; without it, the manhole stays where it is.−£2,424 · 6%
Demolition£7,980 with, £6,380 without. Less to strip out, and no excavation arisings.−£1,600 · 4%
External works£6,830 with, £5,362 without. No new garden boundary walls to either neighbour.−£1,468 · 4%
Doors and windows£7,345 with, £6,220 without. Fewer openings to weatherproof, no skylight.−£1,125 · 3%
Kitchen and bathroom£9,780 with, £9,150 without. The ground-floor WC comes out; the two first-floor bathrooms do not.−£630 · 2%
Decorating£15,942 with, £15,314 without. Slightly less wall area to skim and paint.−£628 · 2%
Water and heating£11,170 with, £10,710 without.−£460 · 1%
Electrical£14,928 with, £14,585 without. 120+ points becomes 115+.−£343 · 1%
Gas£2,170 either way. Same boiler, same flue, same certificate.NO CHANGE
Joinery£4,850 either way. Carried as a prime cost sum against the same joinery package.NO CHANGE

Approved Documents are statutory guidance to the Building Regulations 2010 for England. Compliance is judged against the Requirements in Schedule 1; the Approved Document shows one way of meeting them. Your building control body has the final word on your specific building.

The number that changes how you read a quote

£26,234 of the £38,532 — 68% — is in structure and build-ups alone. An extension buys a hole in the ground, a steel frame, a roof and new fabric. It does not change the rewire, the boiler, the bathrooms or the decorating, because those are pricing the house you already have.

That is why "cost per square metre of extension" misleads people holding a whole- house scheme. Most of a refurbishment budget is not sensitive to whether you extend. Two sections here were identical to the penny, and a third moved by £343 on nearly £15,000.

Not extending is not the same as doing nothing structural

This is the part that gets missed, and it is the reason the saving was 22.7% rather than the 35% the client had in mind.

Taking the extension out did not take the structure out. The renovation-only option still carried:

A steel beam and column. With a new pad foundation, padstones and fire protection, forming an opening through the existing rear structural wall — because the kitchen still opens across the outrigger.
A new opening in the garden elevation. Needled, propped, lintelled and made good inside and out, to take the French doors that replace the extension's glazing.
An existing window blocked up. In brick and block, insulated, and made good both sides — the opening the new arrangement no longer wants.
Two steps down into the kitchen. Formed and finished, because the existing floor levels were only going to be reconciled by the extension's new slab.
The outrigger partitions removed. The existing rear WC and bathroom walls taken out so the kitchen can open up across the whole outrigger.

If the reason you wanted the extension was an open, level kitchen, you are buying steel either way. What changes is how much of it, and whether it comes with foundations and a roof.

The consequence nobody prices: the party wall position

The extension required pockets cut into the party walls of both neighbouring houses. The renovation-only option did not.

That removes a whole class of notifiable work under the Party Wall etc. Act 1996, and with it a set of surveyor appointments, awards and schedules of condition on two sides. It does not necessarily remove the Act — excavation near a neighbour's foundations or work to a party structure can still engage it — but a scheme that stops at your own rear wall gives your neighbours materially less to dissent to. What that is worth in fees is set out in what a party wall agreement costs; what it is worth in programme is often larger, because a dissent runs a clock you do not control.

The honest line in the second quotation

The structural engineer's package on that job was designed for the extension. The renovation-only option does not build it.

So the beam and column forming the new rear opening were priced on our own allowance — roughly a five-metre universal beam and a 152x152x30 UC column — and flagged in the quotation as needing section sizes, a connection design and a pad-foundation design from the engineer before any steel is ordered, with those two lines re-priced against that design either way.

That is worth saying out loud because the alternative is common and looks better. A quotation that silently reused the extension's steel design would have read as more certain and been less true, and the difference would have surfaced as a variation once the real design arrived. If you are comparing two builders on an alternative scheme, ask which of them has told you what is still provisional.

What was separated out rather than deleted

Three items came out of the extension option but were priced individually, so they could be put back one at a time:

Add-backs, priced separately — net of VAT
WhatThe requirementSource
Under-stair ground-floor WCSanitaryware, floor and wall tiling, extract, fire door, lighting, stud enclosure, skim and paint, step infill.£3,050.00
Garden boundary walls to both neighbours215mm facing-brick walls with footings, coping and making good, plus removing the existing rear fence.£3,830.00
Manhole relocation and new below-ground runRelocate the manhole with gullies, waste, soil, rain and vent stacks, and form the new underground drainage run.£1,620.00

Approved Documents are statutory guidance to the Building Regulations 2010 for England. Compliance is judged against the Requirements in Schedule 1; the Approved Document shows one way of meeting them. Your building control body has the final word on your specific building.

Pricing these as discrete add-backs rather than folding them into one reduced number is what lets a client actually choose. It also separates the two kinds of saving: money that goes away because the extension does, and money that is simply a deferred decision.

What this comparison does not tell you

It is one house. One Battersea terrace, one set of drawings, one ground condition. The shape of the finding travels; the figures do not. Your own numbers come from your own drawings.
It is a quotation, not a final account. These are the figures we quoted against a tender package, not what a completed job invoiced. Prime cost sums reconcile, and provisional lines re-price when the design firms up.
It does not price the value of the space. £38,532 buys roughly twenty square metres of ground floor and a kitchen that opens to the garden. Whether that is worth it is a question about your house and how long you will live in it, and no builder should answer it for you.
It does not include the consultants. Architect, structural engineer, party wall surveyor and building control sit outside both figures. Dropping the extension reduces some of those too, which makes the true gap wider than £38,532.

For the general picture across London rather than one job, house extension cost in London 2026 sets out the ranges, and full house renovation cost prices the refurbishment side on its own. To put your own scheme through the same model we price real work with, the estimator itemises it by trade, net of VAT.

Our interest, declared

The larger option is the larger contract, and we build extensions — so the version of this page that served us would push the extension. What actually serves you is asking your builder to price both, on the same drawings, on the same day, and to show you the sections side by side. If the difference is not concentrated the way it is above, ask why.

How to get this comparison for your own house

  1. 01Ask for both options against one set of drawings. Not two conversations weeks apart. The same measured quantities, the same rates, the same day — otherwise you are comparing two builders' moods rather than two schemes.
  2. 02Insist the sections line up. Thirteen sections in one quotation and eight in the other cannot be subtracted. If the structures differ, you cannot see where the money moved, which is the only thing worth seeing.
  3. 03Look for the sections that DON'T change. Gas, joinery, electrical and decorating should be close to identical. If they swing, the two options are not pricing the same house and something else has been changed quietly.
  4. 04Ask what structure survives the smaller option. Removing an extension rarely removes steel. Get the beam, the column, the foundation and the openings named and priced, so the smaller option is not sold as structure-free.
  5. 05Get the add-backs priced individually. A WC, a boundary wall, a drainage run. Separately priced, they are choices. Rolled into one reduced total, they are invisible and they come back as variations.
  6. 06Establish what the engineer actually designed. A structural package drawn for the extension does not size the alternative. Ask which lines are on the builder's allowance and when they get re-priced.
  7. 07Count the party wall consequences on both. Pockets into a neighbour's wall, or excavation below their foundations, are notifiable. A scheme that stops at your own rear wall may take two surveyor appointments off the table.
  8. 08Compare the programmes, not only the totals. Four weeks was the difference here. If you are renting elsewhere, that is a real number that belongs next to the build cost rather than under it.

The one line to take away

Ask for the same house priced both ways, and read the sections rather than the totals. On this job the extension changed two trades substantially, two not at all, and everything else by rounding — and that pattern told the client more about their decision than the 22.7% did.

2VP is the builder, not a marketplace: one contract, one named project lead, and no introducer fee stacked on the build cost. When a scheme has two versions, the same people price both, and you can see which lines moved.

You pay weekly, against work already done10% to mobilise, then weekly against work already done — with 5% held past handover: 2.5% released at practical completion and 2.5% at the end of the 12-month defects period. Your money never gets ahead of the build.
Every variation priced and dated firstNothing is spent on a change until you have approved it in writing, with its cost and its effect on the date.
The measured survey is credited in fullIf you appoint us, the pre-contract survey fee comes off your contract rather than sitting on top of it.
A completion date, in the contractNot an estimate. It is written in, and only a variation you approve can move it.
Common questions

Straight answers

The 2VP Certainty Package

The home you actually want, finished on the date in the contract — and you watch every day of it happen from your phone.

Your number in 60 secondsItemised stage breakdown in 2 minutesSurvey within 7 days

You answer 3 questions. We do the drawings, planning, party wall, trades and snagging.

Before anything is signed
Full measured survey + 3D design visualisation
You see the finished room before you commit to building it
£1,500
RIBA architect design by Nick Elias
Concept, planning and technical drawings by one named architect
£8,000–£15,000
Completion date written into the contract
A date you can plan a life around, not 'TBC at build start'
Included
While we build
No variation without your written approval
Nothing is added to your bill that you did not sign for first
Included
Friday video walkthrough of your site, every week
You know what happened this week without driving over
£1,200/yr
One named project lead, one channel, 24-hour response
You never chase a company — you message a person
Included
Daily photo diary + client dashboard
Everything photographed before it is covered up
Included
Fixtures at our trade pricing, passed through at cost
Our discount is yours, not a margin we keep quiet about
10–20% on materials
After we hand over
6-month snagging visit
We come back once the house has moved and settled
£750
12-month workmanship warranty on second-fix fittings, signed by the trades
The people who built it are on the hook for it, by name
Included
Annual check-ins for 2 years
We come back. Every year. No charge.
Included
Our guarantee
We finish on the agreed date, or we pay you £500 for every week we are late.
The date is in the contract, and so is this. Only a variation you approve can move it.
What you are not risking
  • 10% to mobilise, then weekly against work already done — with 5% held past handover: 2.5% released at practical completion and 2.5% at the end of the 12-month defects period
  • £550 survey fee credited in full against your contract
  • Every variation priced and signed before a penny is spent
4.8★ from 16 Google reviews — including the 1-star, published in full.
Get my price in 60 seconds

No email needed to see your range. Quotes hold for 21 days, then materials re-price.

We are not the cheapest. If price is the only factor, we may not be the right fit — and that is fine.

Get my price in 60 secondsExtensionsExtension costs by areaBuilders in your areaAll cost guides
If this is your project

The home you actually want, finished on the date in the contract — and you watch every day of it happen from your phone.

How fast
  • Your number in 60 seconds
  • Itemised stage breakdown in 2 minutes
  • Survey within 7 days
What you do

You answer 3 questions. We do the drawings, planning, party wall, trades and snagging.

What protects you
  • 10% to mobilise, then weekly against work already done — with 5% held past handover: 2.5% released at practical completion and 2.5% at the end of the 12-month defects period
  • £550 survey fee credited in full against your contract
  • Every variation priced and signed before a penny is spent

The date is a term of the contract. We finish on the agreed date, or we pay you £500 for every week we are late.

Do not take our word for it

4.8 from 16 Google reviews

Every review is published in full on our reviews page, including the one-star. Google is the only platform we quote a rating for, because it is the only one we can evidence.

★★★★★
As a structural engineer, I've collaborated with 2VP Projects Ltd on several residential projects in London. Their attention to detail, proactive site management, and clear communication make every stage—from design to execution—smooth and efficient. It's rare to find a contractor who values both precision and professionalism at this level. A truly reliable partner.
Igors Smirnovs · Structural engineer we have worked with · June 2025
★★★★★
Great company to work with. Professional, reliable and easy to deal with. Vladimir and the team are always responsive, straightforward and genuinely care about doing things properly. I've had a very positive experience working with 2VP and would happily recommend them.
Sheen Delicatessen · Business client · August 2026
★★★★★
Extension went smoothly from start to finish. Communication was great throughout, and the team delivered exactly what we asked for. Thank you, 2VP!
Dan Martea · August 2026
Warranties and protections

What is covered, and by whom

A builder’s own guarantee is worth exactly as much as the company standing behind it. Here is what comes as standard, what you can add, and what has to come from somebody other than us — set out in full on our insurance and guarantee page.

Included in the contract
  • 12-month workmanship warranty on second-fix fittings
  • £5M public liability
  • £10M employer's liability
  • £2M professional indemnity
Optional, on request
  • HomePro insurance-backed guarantee, 10 years
  • Priced at 2.5% of the contract sum
  • Underwritten by an insurer, so it survives us
Not from us
  • 10-year structural warranty on a new dwelling (NHBC / LABC / Premier)
  • Professional fees — architect, engineer, building control
  • We will tell you when you need one rather than let you find out