Order this now · July 2026

Lead-time & price watch

Know what to order early — before it quietly stalls your client's job. Live London lead times and price moves, from a contractor buying these packages every week. One glance tells you what to release now.

Updated 1 July 2026
This month’s call

Release aluminium glazing and fabricated steel packages the moment structural drawings are signed off — both are running 8–12 weeks and are the most common cause of a stalled site this summer.

PackageLead timeTrend
Fabricated steelOrder at the end of Stage 4, not on site.6–8 wks Rising
Aluminium bi-folds / slidersThe classic programme-killer — release early.8–12 wks Rising
Rooflights (Velux/Fakro stock)1–2 wks Stable
Bespoke rooflights / structural glass10–14 wks Stable
Bespoke joinery / kitchensIn-house via Selection.Works — we hold the programme.8–12 wks Stable
Brick (standard London stock)3–4 wks Easing
Underfloor heating manifolds2–3 wks Stable

Prices moving too? See the material moves on the Cost Index.

Cost of the Month

Real London build costs, every month.

The figures you need for a Stage-1 client conversation — from a live London contractor, not a paywalled national dataset.

One email a month. Live London £/m², what’s moving on price and lead times, and one detail teardown. No spam, unsubscribe any time.

For the scheme on your desk

Put a real cost against it

Fill in a scope template and you get an elemental cost plan back by RIBA element — from a contractor building in London this week, not a rate book. Free, and it stays yours whoever ends up on site.

Cost a project020 8050 8968