Order this now · July 2026
Lead-time & price watch
Know what to order early — before it quietly stalls your client's job. Live London lead times and price moves, from a contractor buying these packages every week. One glance tells you what to release now.
Updated 1 July 2026
This month’s call
Release aluminium glazing and fabricated steel packages the moment structural drawings are signed off — both are running 8–12 weeks and are the most common cause of a stalled site this summer.
Prices moving too? See the material moves on the Cost Index.
Cost of the Month
Real London build costs, every month.
The figures you need for a Stage-1 client conversation — from a live London contractor, not a paywalled national dataset.
One email a month. Live London £/m², what’s moving on price and lead times, and one detail teardown. No spam, unsubscribe any time.