Lead-time & price watch
Know what to order early — before it quietly stalls your client's job. Live London lead times and price moves, from a contractor buying these packages every week. One glance tells you what to release now.
Release aluminium glazing and fabricated steel packages the moment structural drawings are signed off — both are running 8–12 weeks and are the most common cause of a stalled site this summer.